Two Workers, One Job

  • Easy
  • Work, speed and rate puzzles
  • Tests: Adding rates, never times

The puzzle

Working alone, one labourer finishes a job in 12 days and another finishes the same job in 18.

Working together at their usual speeds, how long do they take?

Stuck?

One at a time, smallest first. Open only as many as you need — the whole point of the puzzle is the part you work out yourself.

Hint 1

Averaging 12 and 18 gives 15, which is longer than one of them takes alone - so it cannot be right.

Hint 2

Ask what fraction of the job each does in one day.

Show the answer Hide the answer

7.2 days, or 7 days and about 5 hours.

How to get there

In one day the first does 1/12 of the job and the second 1/18.

Together they do 1/12 + 1/18 = 3/36 + 2/36 = 5/36 of the job per day.

One whole job at 5/36 per day takes 36/5 = 7.2 days. Note it is less than either alone, which is the sanity check that catches averaging.

The technique worth keeping

Turn "takes n days" into "does 1/n per day" immediately. Rates add; times do not, and the answer must always come out shorter than the faster worker alone.