Two Workers, One Job
The puzzle
Working alone, one labourer finishes a job in 12 days and another finishes the same job in 18.
Working together at their usual speeds, how long do they take?
Stuck?
One at a time, smallest first. Open only as many as you need — the whole point of the puzzle is the part you work out yourself.
Hint 1
Averaging 12 and 18 gives 15, which is longer than one of them takes alone - so it cannot be right.
Hint 2
Ask what fraction of the job each does in one day.
Show the answer Hide the answer
7.2 days, or 7 days and about 5 hours.
How to get there
In one day the first does 1/12 of the job and the second 1/18.
Together they do 1/12 + 1/18 = 3/36 + 2/36 = 5/36 of the job per day.
One whole job at 5/36 per day takes 36/5 = 7.2 days. Note it is less than either alone, which is the sanity check that catches averaging.
The technique worth keeping
Turn "takes n days" into "does 1/n per day" immediately. Rates add; times do not, and the answer must always come out shorter than the faster worker alone.