Time and Work

  • Quantitative Aptitude
  • 3 worked examples
  • 5 rules to know

What it is

Days do not add; rates do. If A takes 10 days, A does one tenth of the job a day, and rates can be summed, subtracted and scaled freely. Converting to rates in the first line is the whole technique.

The faster version is to work in units: take the LCM of the given days as the total work, and everybody’s rate becomes a whole number. No fractions for the rest of the question.

What you need to know

  1. If a job takes n days, the rate is 1/n of the job per day. Rates add; days do not.
  2. Together, A and B take 1/(1/a + 1/b) = ab/(a + b) days.
  3. Let total work be the LCM of the given times. Rates then come out as whole units per day.
  4. A leaking pipe is a negative rate - subtract it from the filling rates.
  5. If A is n times as efficient as B, A takes 1/n of the time.

Worked examples

Try each one before opening the answer. A solution you have read is not a solution you can produce under time pressure, which is the only kind that counts.

Q1 A can do a job in 12 days and B in 18. Working together, how long do they take?

Show the answer Hide the answer

7.2 days.

Take the total work as LCM(12, 18) = 36 units. A does 3 units a day, B does 2, so together 5. 36/5 = 7.2 days. The formula ab/(a + b) gives 216/30, which is the same.

Q2 A and B together finish a job in 8 days. A alone takes 12. How long does B alone take?

Show the answer Hide the answer

24 days.

Work in rates. Together they do 1/8 a day and A does 1/12, so B does 1/8 − 1/12 = 3/24 − 2/24 = 1/24. B alone takes 24 days. Subtracting the days - 12 from 8 - is meaningless, and is the error here.

Q3 Two pipes fill a tank in 20 and 30 minutes. A third empties it in 40. With all three open, how long does the tank take to fill?

Show the answer Hide the answer

17 and 1/7 minutes, about 17.14.

Take 120 units as the tank. The fillers add 6 and 4 units a minute; the drain removes 3. Net 7 units a minute, so 120/7 = 17.14 minutes. The drain is a negative rate, which is why it subtracts rather than adding to the time.

Where people lose marks

  • Adding or subtracting days instead of rates.
  • Forgetting to subtract a leak, or subtracting it from the days rather than the rate.
  • Using the ab/(a+b) shortcut with three workers. It only holds for two.